Blog

Effective
Representation

Powerful Results

Competitive
Advantage

Can Do

Responsive

Positivity

Smart

Community
Impact

Collaborative
Approach

Client
Focused

Streamlined
Operations

Effective
Representation

Community
Impact

Collaborative
Approach

Powerful Results

Smart

Streamlined
Operations

Blog

Competitive
Advantage

Positivity

Client
Focused

Can Do

Responsive

BU Synthetic Turf Field Project Trips Up Architect

May 30, 2025

 

Statute of Repose No Defense Against Lawsuit

A Massachusetts statute bars tort lawsuits arising from defective or neg­ligent design, planning, construction or general administration of build­ings and improvements, unless filed within six years after construction completion.

This statute is known in the construction industry as the “statute of repose.” Statutes of repose operate much like statutes of limi­tations. Both protect potential defendants from having to respond to lawsuits filed many years after the alleged wrongdoing, but there are significant differences. Stat­utes of limitations can be suspended for various reasons, such as when plaintiffs cannot discover their injuries, or cannot de­termine responsible parties. This gives flexi­bility to the end point of the limitations pe­riods in statutes of limitations.

Boston University’s Charles River campus spans 113 acres centered along Commonwealth Avenue between Massachusetts Avenue and Packard’s Corner.

In contrast, statutes of repose cannot be suspended for any reason. They impose ab­solute time limits on when plaintiffs can sue potential defendants. Statutes of repose bar plaintiffs’ claims after the statutory period expires, even when plaintiffs’ injuries or damages occur later or are not discoverable within the limited timeframe.

However, last month in Trustees of Bos­ton University v. Clough, Harbour & Associ­ates LLP, the Massachusetts Supreme Judi­cial Court ruled, in effect, that the statute of repose limiting suits for design defects can be contractually negated.

Boston University engaged an architec­tural firm in 2012 to design a synthetic turf athletic field above a parking structure de­signed by the same firm. The contract pro­vided for about $970,000 in payments to the architects for professional services. It also required the architects, “to the fullest extent permitted by law,” to indemnify the univer­sity from all expenses, including attorney’s fees, caused by the architects’ negligence.

A $25K Defect

After the athletic field went into service in 2013, it became apparent that the field had design defects that rendered it unsafe. The defects arose from the architects’ fail­ure to account for seasonal expansion of joists in the underlying parking structure.

The university spent $25,000 to remedy the defect, and demanded indemnification from the architects, who refused to pay for the remediation. In 2020, more than six years after the athletic field was first used, the university sued the architects in Supe­rior Court for breach of the indemnification.

The architects moved for summary judg­ment, seeking dismissal of the university’s suit under the statute of repose.

The Superior Court judge agreed, and ruled in 2024 that the statute of repose barred the university’s contractual indemni­fication claim. The Supreme Judicial Court granted an application for direct appellate review.

The SJC noted at the outset of its deci­sion that the statute of repose bars negli­gence claims for design and construction defects, unless the claim is brought within six years after completion.

The SJC also noted that a negligence claim is an “action in tort,” but the universi­ty’s suit included a claim against the archi­tects for breach of the indemnification agreement, which is an “action in contract.”

Lawsuit Created an Unusual Situation

The SJC recognized that the university’s lawsuit created an unusual situation under the statute of repose, because the university was seeking compensation under a contrac­tual indemnification clause for a loss that resulted from the architects’ negligence.

Therefore, according to the SJC, it was necessary to look beyond whether the uni­versity’s suit arose in tort on in contract, and to instead examine the “gist of the ac­tion.”

The SJC next compared the differences between actions in tort and actions in con­tract. Actions in tort arise where defendants fail to meet standards imposed by law, while actions in contract arise where defen­dants fail to meet standards set by the de­fendants’ promises made in their agree­ments with plaintiffs.

The SJC determined that the gist of the university’s claim against the architects was essentially “the enforcement of a contract for indemnification,” observing that the ar­chitects explicitly promised to indemnify the university from costs incurred as a re­sult of the architects’ negligence.

Time Limits Can Be Negotiated

Therefore, the university’s claim was con­tractual in nature, and the statute of repose did not bar it.

The SJC reversed the Superior Court’s dismissal of the university’s contract claim, while stating that in order for the university to prevail, it must prove the existence of an enforceable indemnification agreement, the occurrence of an event triggering the archi­tects’ indemnification obligation, the giving of adequate notice to the architects, and the architects’ breach of the indemnification agreement.

The statute of repose remains in effect for tort claims in building design and con­struction defect cases, but the SJC’s deci­sion shows that project developers can avoid the strict six-year limit, by including properly drafted indemnification clauses in their contracts with design professionals and contractors.

Download the article as seen in Banker & Tradesman on April 28, 2025. Learn more about Christopher R. Vaccaro.

GET IN TOUCH NOW

    (978) 470-8400 Give us a ring to speak to a member of our team in the strictest confidence.
    • WE DELIVER POWERFUL RESULTS
    • DEDICATION IS OUR ADVANTAGE
    • COLLABORATIVE APPROACH