Tag Archives: #marealestate

Woods Hole Project Illustrates Coastal Permitting Challenges

Marine Researchers Secure Dock Upgrade

The deepwater port at Woods Hole on Cape Cod has hosted research ves­sels for the Woods Hole Oceanographic Institu­tion (WHOI) for nearly 100 years.

WHOI has a world­wide reputation for oceanography. Its Iselin Marine Facility, located in the middle of Woods Hole village, is the homeport for WHOI’s ocean-going research vessels and underwater vehicle operations. The facility is also a hub for developing and testing new technologies, and an important contributor to the regional blue economy.

Unfortunately, the facility’s 57-year-old dock is nearing the end of its useful life, while facing threats from rising sea levels and coastal erosion.

Many Permits, Years of Review

WHOI determined several years ago that repairs and maintenance to the existing dock, without major capital improvements, were not economically feasible, so the insti­tute developed plans to replace the facility with a new Complex for Waterfront Access to Exploration and Research (CWATER).

Woods Hole Oceanographic Institution waterfront is a hub for oceanography and a major contributor to the regional blue economy.

The project will include a redesigned and rebuilt pile-supported dock, bulkhead re­placement, dredging, new facilities for ro­botic vessels and a new building hosting labs and shops focused on water-dependent activities. CWATER will provide WHOI with a more resilient marine facility designed to withstand anticipated sea level rises and se­vere weather events for the next 80 years.

CWATER will impact several coastal re­source areas that are subject to state regula­tion. Therefore, WHOI was required to sub­mit an environmental notification form to the state Executive Office of Energy and Environmental Affairs for the project under the Massachusetts Environmental Policy Act (MEPA).

WHOI enjoyed an early success in the permitting process in 2020, when the secre­tary determined that WHOI could proceed without filing an environmental impact re­port for CWATER under MEPA.

However, WHOI still needed several per­mits for CWATER, including a Chapter 91 waterways license and a water quality cer­tificate from the Massachusetts Department of Environmental Protection, a wetlands order of conditions from the Falmouth Con­servation Commission, authorization from the U.S. Army Corp of Engineers, a National Pollutant Discharge Elimination System permit from the U.S. Department of Envi­ronmental Protection and federal consis­tency review from the Office of Coastal Zone Management.

WHOI was also required to consult with state and federal agencies to minimize the project’s impacts on nearby eelgrass mead­ows.

Waterfront permitting in Massachusetts is not for the faint of heart.

Community Feedback Built Consensus

After years of public hearings, neighbor­hood meetings and design changes to ac­commodate engineering challenges and pub­lic and governmental input, WHOI obtained its final permits for CWATER this year.

WHOI notably secured its permits with­out having to endure litigation or appeals. This success would not be possible without excellent public relations, and local appre­ciation for WHOI’s mission and reputation.

Part of WHOI’s strategy involved creation of a community advisory committee to pro­vide a mechanism for communication and feedback. WHOI also co-founded Resilient Woods Hole, which helps its Woods Hole neighbors to better understand how infra­structure improvements along Wood Hole’s coast are essential to protecting the village from the effects of climate change.

$100M Pier Project

However, one major challenge remains for CWATER – obtaining financing for a project that is expected to take seven years to complete at a cost of over $100 million.

WHOI is a private nonprofit that is not di­rectly tied to any governmental entities or public universities, so it depends heavily on federal and state grants and philanthropy. WHOI initially obtained a few million dol­lars in state grants for CWATER, and it also received some private grants for design and permitting. Construction can now begin in earnest.

WHOI had hoped to obtain major funding from the federal government, but those sources were largely eliminated from the federal budget this year.

For now, CWATER is expected to move forward in phases, as funding becomes available. The first phase of the project, scheduled to begin next year, will involve the construction of a robotics vehicle port with funds from the U.S. Navy. Finding reli­able sources of funding for later phases re­mains a challenge.

“CWATER will be an advanced, resilient facility that will provide access to the sea for our scientists, engineers, seafarers and technicians for the rest of this century,” Rob Munier, WHOI’s vice president of marine fa­cilities who has quarterbacked this project since its inception, told me. “It will serve as a classroom for future generations of oceanographers and an incubator for new technologies, ensuring continued leadership in our basic understanding of the ocean and enabling the discovery of solutions to criti­cal problems facing the Earth system – and humanity. The process of delivering CWA­TER is complex and we have achieved the critical ‘shovel-ready’ milestone. Now it is time to get wet!”

Download the article as seen in Banker & Tradesman on September 29, 2025. Learn more about Christopher R. Vaccaro.

SJC Limits Landlords’ Use of Security Deposits

Court Favors Tenant in Dispute Over Cleaning Requirement

The Massachusetts Supreme Judicial this month ruled on whether a residen­tial landlord properly used a tenant security deposit to offset the landlord’s cost of clean­ing a vacated dwelling.

The Massachusetts security deposit statute imposes strict requirements on residential landlords. Security deposits cannot exceed one month’s rent. Landlords must give resi­dential tenants written receipts for security deposits, with sworn statements of condition.

Security deposits must be held in special bank accounts and tenants are entitled to yearly notices identifying banks holding de­posits, with account numbers and annual in­terest payments on their security deposits.

A recent Supreme Judicial Court ruling favored tenants in a dispute over a lease requirement to hire professional cleaners when moving out.

Residential landlords often inadvertently violate the statute and egregious violations can result in judgments requiring landlords to pay triple the security deposit to tenants plus attorney’s fees.

Landlords can only deduct from security deposits for unpaid rent and water charges, unpaid real estate taxes and reasonable amounts necessary to repair damage caused to the dwelling unit but specially excluding “reasonable wear and tear.” Landlords who deduct from security deposits for damage must provide tenants with sworn state­ments with supporting documentation.

A major Los Angeles-based residential landlord recently learned in Peebles v. JRK Property Holdings Inc., that even sophisti­cated landlords can get tripped up by the statute.

Tenant Challenges Lease Requirements

JRK Property Holdings uses its own stan­dard form of residential lease. Its lease re­quired tenants to paint and professionally clean their apartments, including carpet cleaning, at the end of their leases.

JRK’s lease authorized it to apply specific charges for the cost of painting, carpet cleaning and cleaning specific items such as bathroom and kitchen fixtures, doors, win­dows and cabinets. It reserved the right to deduct painting and cleaning charges from tenant security deposits if tenants failed to satisfy these obligations.

When one of its tenants, Branda Peebles, vacated her apartment without using pro­fessional cleaning services, JRK deducted $115 from her security deposit.

Peebles filed a putative class action law­suit against JRK in Suffolk Superior Court for an alleged violation of the security de­posit statute, seeking triple her security de­posit. She claimed that JRK’s cleaning costs arose from “reasonable wear and tear” on the apartment and therefore JRK’s deduc­tion from her security deposit violated the statute.

Federal Judge Returns Case to SJC

Because JRK is incorporated and head­quartered in California, it was able to re­move the case to federal court, but the case returned to Massachusetts when the federal judge certified questions regarding the Mas­sachusetts security deposit statute to the Supreme Judicial Court.

The federal court asked the SJC to an­swer, first, whether a landlord deducting the cost of painting, carpet repair and simi­lar refurbishments from a tenant security deposit, violates the security deposit stat­ute; and second, whether a clause in a lease allowing the landlord to deduct the cost of professionally cleaning violates the statute.

The SJC first considered whether charging a tenant for painting and carpet cleaning vio­lated the statute. Peebles argued that paint­ing and carpet cleaning address reasonable wear and tear instead of damage to the prem­ises, so the charges were not deductible.

The SJC noted that the statute does not define the term “reasonable wear and tear.” Accordingly, whether or not damage consti­tutes reasonable wear and tear is fact-spe­cific to each case, depending on the condi­tion of the premises at the outset of the lease, the use of the premises, the expected deterioration of the premise because of such use and the length of the tenant’s oc­cupancy.

The SJC declined to set a firm rule that all damage requiring painting or cleaning is reasonable wear and tear, but noted that normal use of leased premises will result in gradual deterioration and security deposit deductions for such reasonable wear and tear violate the statute.

The SJC next determined that JRK’s lease provision requiring tenants to profession­ally clean their premises at the end of the lease, under threat of security deposit de­ductions, is in effect a requirement that ten­ants forfeit security deposits to pay for rea­sonable wear and tear.

The SJC ruled that the lease provision vi­olates the statute and is void and unenforce­able. Based on the SJC’s decision, the fed­eral court is likely to rule in favor of Peebles and it might require JRK to pay triple her se­curity deposit plus her attorney’s fees.

Peebles filed her Superior Court suit in 2019. Her case spent several years working its way through Superior Court, federal court and the SJC.

The possibility remains that Peebles’ case will be certified as a class action, which will further JRK’s legal entanglements and risk. This is a lot of exposure for JRK over a $115 cleaning charge.

Download the article as seen in Banker & Tradesman on August 25, 2025. Learn more about Christopher R. Vaccaro.

Invasive Weed Trips Up Builder in Pepperell

Appeals Court Favors Homeowners in Consumer Protection Lawsuit

Young parents buy­ing newly con­structed homes have many concerns: construction quality, neighborhood safety, local public schools and their financial ability to manage mortgage pay­ments and carrying costs.

Whether their builder may have know­ingly spread loam infused with an invasive weed and glass and metal debris upon their property, should not be among them. But this happened to a family that bought a new home in Pepperell.

Peter Cricones acquired a vacant gravel pit in 2015 to develop a residential subdivi­sion. He used loam from various sources for his project, including some remaining from the gravel pit.

Cricones’ excavation contractor saw that this loam contained Japanese knotweed, a highly invasive species that dominates yards unless its rhizomes and root structure are eradicated. The excavator warned Cri­cones not to combine this loam with the rest, but Cricones disregarded this advice and used knotweed-infested loam for the subdivision.

Joseph and Kim Trites bought a home from Cricones in 2017, unaware of the un­seen knotweed contamination. Before long, knotweed took over their yard, foundation and areas beneath their deck, and erupted through their paved walkways. The soil in their lawn also harbored glass and metal de­bris, rendering their yard unsafe.

Japanese knotweed. Under Massachusetts Chapter 93A, developers are liable for failure to disclose known defects to homebuyers.

Complaints Relations Quickly Turn Hostile

After Cricones made fruitless efforts to remove the knotweed, relations between the parties grew hostile. The Triteses posted warning signs about the knotweed infesta­tion, and Cricones countered with threats and vulgar gestures.

In 2018, the Triteses sued Cricones in Su­perior Court for nuisance, negligence, breach of the implied covenant of good faith and fair dealing and unfair and decep­tive practices in violation of Massachusetts General Laws Chapter 93A.

After the trial, Cricones moved for a di­rected verdict in his favor on the nuisance and implied covenant claims. The trial judge denied the motion and sent those claims to the jury.

The jury found Cricones liable for nui­sance and breach of the implied covenant of good faith and fair dealing, and awarded the Triteses $186,000. In addition, the judge ruled that Cricones violated Chapter 93A, and awarded the Triteses the same $186,000 as the jury, plus the Triteses’ attorney’s fees and costs.

The judge declined to award the Triteses multiple damages, after finding that Cri­cones’ conduct was not willful and knowing.

Implied Covenant Claim Overruled

Cricones appealed, and the Appeals Court rendered its judgment on his appeal last February.

The Appeals Court’s decision first ad­dressed the jury’s verdicts against Cricones for nuisance and breach of the implied cov­enant. It noted that a nuisance claim must be based on an invasion of an owner’s prop­erty rights, originating from someone else’s property.

Because the knotweed infestation and the glass and metal debris existed on the Triteses’ property, and did not emanate from other property, the court ruled that the Triteses could not successfully maintain their nuisance claim.

The court also reversed the jury’s verdict against Cricones for breach of the implied covenant of good faith and fair dealing.

Massachusetts courts recognize this im­plied covenant in every contract. The implied covenant prohibits contracting parties from taking actions that, although not expressly addressed in a written contract, would effec­tively prevent other contracting parties from realizing the benefits of their bargains.

The court noted that the implied cove­nant cannot operate beyond the scope of the written contract, and the Triteses’ con­tract with Cricones did not require him to disclose the soil contaminants.

The court overruled the verdict against Cricones on that claim, stating that purchas­ers of new homes should instead rely on ex­press warranties and disclosures in their contracts, the implied warranty of habitabil­ity as to construction defects and protec­tions under Chapter 93A.

Developers Subject to Home Sales Disclosures

The court next addressed the Chapter 93A judgment against Cricones.

It observed that Chapter 93A does not apply to isolated sales of private homes, but the statute does apply to sales by develop­ers like Cricones.

When developers fail to disclose known material defects in a property, their non-dis­closure can violate Chapter 93A, even if their contracts with homebuyers do not re­quire disclosure. Developers cannot be held liable under Chapter 93A for non-disclosure of defects unknown to them, or for defects that homebuyers are aware of.

But in the Triteses’ case, Cricones knew about the soil contamination, and the Trite­ses did not, so the court upheld the Chapter 93A judgment against Cricones.

While Cricones prevailed on his appeal of the nuisance and implied covenant judg­ments, the court upheld the $186,000 Chap­ter 93A judgment against him, leaving Cri­cones where he was before he appealed, but with a bigger legal bill to pay.

Download the article as seen in Banker & Tradesman on July 28 2025. Learn more about Christopher R. Vaccaro.

With Ordinance, Boston Targets Climate Change

BERDO Requires Upgrades of Commercial Properties

Boston’s City Council origi­nally passed the Building Energy Re­porting and Disclosure Ordinance (BERDO) in 2013, to better un­derstand the role that larger residential and commercial buildings play in greenhouse gas emissions. BERDO has been periodi­cally amended since then, and it now im­poses significant reporting and emissions standards on Boston’s larger buildings.

BERDO requires that owners of non-resi­dential buildings with more than 20,000 square feet of floor area, and owners of resi­dential buildings with more than 15 dwell­ing units, annually report to the Boston Air Pollution Control Commission their energy and water usage, and their compliance with BERDO’s emissions standards. Private building owners’ annual reports must in­clude information on greenhouse gas emis­sions, building uses, use of renewable en­ergy certificates and sources of energy purchased for buildings.

In 2026, and every five years thereafter, building owners must provide independent third-party verifications of their reported data for the previous five years. Owners can require separately metered commercial ten­ants to submit the BERDO reports for their leased premises. The city itself is subject to a much less burdensome version of this re­porting requirement.

The Air Pollution Control Commission must disclose on the city’s website energy and water usage and emissions information for each building covered by BERDO. That commission has promulgated detailed regu­lations and policies for interpreting and im­plementing BERDO, along with a proce­dural framework for the ordinance.

The HVAC systems on the roof of 888 Boylston St. in Boston. Boston’s building emissions-control law adds new requirements for larger buildings to start lowering their emissions.

In addition to the reporting requirements, beginning this year BERDO imposes green­ house gas emission standards on larger buildings. The standards require substantial reductions in those emissions every five years. However, buildings with 20,000 or more square feet but less than 35,000 square feet, and those with 15 to 34 dwelling units, do not have to comply with emissions stan­dards until 2031, reporting for 2030 emis­sions. By 2050, all covered buildings are ex­pected to produce zero emissions.

Option to Buy Renewable Energy Certificates

BERDO allows owners to mitigate green­house gas emissions by acquiring renewable energy certificates from non-greenhouse gas emitting sources, by purchasing energy from non-emitting renewable sources, or by making “alternative compliance payments.” The initial cost of those payments is $234 per metric ton of greenhouse gas, subject to periodic review.

The option for owners to make these pay­ments is, in essence, a small scale “cap and trade” program that places emissions limits on greenhouse gases but allows owners to exceed those limits by making payments. This amounts to a tax on greenhouse gas emissions, which incentivizes owners to minimize those emissions.

Alternative compliance payments are paid into the city’s Equitable Emissions In­vestment Fund, which is dedicated to pro­gressive initiatives such as improving and promoting affordable housing, economic in­clusion for minorities and women, work­force development training programs, com­munity housing ownership and renewable energy infrastructure. Funds are also avail­able for improving air quality and tenants’ indoor environments.

BERDO establishes a review board with significant power. The review board may approve individual compliance schedules for owners, as an alternative to the pre­scribed emissions standards. It can approve hardship compliance plans, allowing less stringent emissions standards for buildings with historic designations, affordable hous­ing refinancing timelines, long-term energy contracts, or financial hardships. The re­view board also considers applications for expenditures from the Equitable Emissions Investment Fund.

Board Responsible for Enforcement Decisions

Perhaps most importantly, the review board is empowered to enforce BERDO’s mandates. It can assess fines and seek court-ordered injunctions against noncom­pliant private building owners and commer­cial tenants.

For noncompliance of reporting require­ments, the fine is up to $150 or $300 per day, depending on building size. Fines for non­compliance with emissions standards are up to $300 or $1,000 per day, again depend­ing on building size. If a third-party verifier finds a discrepancy in an owner’s reporting, the owner is subject to a fine of between $1,000 and $5,000. The review board may grant reductions or waivers of fines. Own­ers can appeal fines assessed against them to the Air Pollution Control Commission.

It is noteworthy that city-owned proper­ties, including some 10,000 housing units owned or managed by the Boston Housing Authority, are excused from the review board’s fines and injunctions. Without the threat of review board penalties, the city has less incentive than private property owners to comply with BERDO. It remains to be seen if the city will fully comply with BERDO’s requirements out of a sense of fairness and civic duty.

Boston has a land area of about 48 square miles, with roughly 675,000 residents. For a planet with over 8 billion people, BERDO cannot provide meaningful climate change mitigation by itself, but one has to start somewhere.

 

Download the article as seen in Banker & Tradesman on June 30, 2025. Learn more about Christopher R. Vaccaro.

BU Synthetic Turf Field Project Trips Up Architect

 

Statute of Repose No Defense Against Lawsuit

A Massachusetts statute bars tort lawsuits arising from defective or neg­ligent design, planning, construction or general administration of build­ings and improvements, unless filed within six years after construction completion.

This statute is known in the construction industry as the “statute of repose.” Statutes of repose operate much like statutes of limi­tations. Both protect potential defendants from having to respond to lawsuits filed many years after the alleged wrongdoing, but there are significant differences. Stat­utes of limitations can be suspended for various reasons, such as when plaintiffs cannot discover their injuries, or cannot de­termine responsible parties. This gives flexi­bility to the end point of the limitations pe­riods in statutes of limitations.

Boston University’s Charles River campus spans 113 acres centered along Commonwealth Avenue between Massachusetts Avenue and Packard’s Corner.

In contrast, statutes of repose cannot be suspended for any reason. They impose ab­solute time limits on when plaintiffs can sue potential defendants. Statutes of repose bar plaintiffs’ claims after the statutory period expires, even when plaintiffs’ injuries or damages occur later or are not discoverable within the limited timeframe.

However, last month in Trustees of Bos­ton University v. Clough, Harbour & Associ­ates LLP, the Massachusetts Supreme Judi­cial Court ruled, in effect, that the statute of repose limiting suits for design defects can be contractually negated.

Boston University engaged an architec­tural firm in 2012 to design a synthetic turf athletic field above a parking structure de­signed by the same firm. The contract pro­vided for about $970,000 in payments to the architects for professional services. It also required the architects, “to the fullest extent permitted by law,” to indemnify the univer­sity from all expenses, including attorney’s fees, caused by the architects’ negligence.

A $25K Defect

After the athletic field went into service in 2013, it became apparent that the field had design defects that rendered it unsafe. The defects arose from the architects’ fail­ure to account for seasonal expansion of joists in the underlying parking structure.

The university spent $25,000 to remedy the defect, and demanded indemnification from the architects, who refused to pay for the remediation. In 2020, more than six years after the athletic field was first used, the university sued the architects in Supe­rior Court for breach of the indemnification.

The architects moved for summary judg­ment, seeking dismissal of the university’s suit under the statute of repose.

The Superior Court judge agreed, and ruled in 2024 that the statute of repose barred the university’s contractual indemni­fication claim. The Supreme Judicial Court granted an application for direct appellate review.

The SJC noted at the outset of its deci­sion that the statute of repose bars negli­gence claims for design and construction defects, unless the claim is brought within six years after completion.

The SJC also noted that a negligence claim is an “action in tort,” but the universi­ty’s suit included a claim against the archi­tects for breach of the indemnification agreement, which is an “action in contract.”

Lawsuit Created an Unusual Situation

The SJC recognized that the university’s lawsuit created an unusual situation under the statute of repose, because the university was seeking compensation under a contrac­tual indemnification clause for a loss that resulted from the architects’ negligence.

Therefore, according to the SJC, it was necessary to look beyond whether the uni­versity’s suit arose in tort on in contract, and to instead examine the “gist of the ac­tion.”

The SJC next compared the differences between actions in tort and actions in con­tract. Actions in tort arise where defendants fail to meet standards imposed by law, while actions in contract arise where defen­dants fail to meet standards set by the de­fendants’ promises made in their agree­ments with plaintiffs.

The SJC determined that the gist of the university’s claim against the architects was essentially “the enforcement of a contract for indemnification,” observing that the ar­chitects explicitly promised to indemnify the university from costs incurred as a re­sult of the architects’ negligence.

Time Limits Can Be Negotiated

Therefore, the university’s claim was con­tractual in nature, and the statute of repose did not bar it.

The SJC reversed the Superior Court’s dismissal of the university’s contract claim, while stating that in order for the university to prevail, it must prove the existence of an enforceable indemnification agreement, the occurrence of an event triggering the archi­tects’ indemnification obligation, the giving of adequate notice to the architects, and the architects’ breach of the indemnification agreement.

The statute of repose remains in effect for tort claims in building design and con­struction defect cases, but the SJC’s deci­sion shows that project developers can avoid the strict six-year limit, by including properly drafted indemnification clauses in their contracts with design professionals and contractors.

Download the article as seen in Banker & Tradesman on April 28, 2025. Learn more about Christopher R. Vaccaro.

North Attleborough Landlord Liable Under ‘Unfair Practices’ Statute

 

Failed Bid for Adjacent Land Led to Lease Breaches

Now and then, a commercial land­lord engages in conduct so peculiar, that others can only shake their heads in be­wilderment. That was the case in H1 Lincoln, Inc. v. South Washing­ton Street, LLC.

Entities controlled by Alfredo Dos Anjos own several properties in a North Attlebor­ough area known as “Auto Road.” Two of Dos Anjos’s limited liability companies signed a long-term lease with Majestic Honda as tenant in 2016. Majestic planned to redevelop the site as a car dealership.

The lease allowed the Dos Anjos LLCs to review and approve Majestic’s plans, with a limited right to terminate the lease if they did not approve the plans. The LLCs agreed to cooperate with Majestic’s permitting ap­plications.

Lease Negotiations Sour

Majestic provided a site plan to the Dos Anjos LLCs in 2017, showing demolition and replacement of one building, and renova­tion of another on the leased premises. The plan also disclosed that Majestic intended to use adjacent property, recently acquired by Majestic, for inventory display and park­ing. Dos Anjos had unsuccessfully tried to purchase the adjacent property.

When Dos Anjos learned of this purchase by Majestic, his relationship with Majestic soured. The LLCs did not respond to Majes­tic’s initial plan submittal. When Majestic re­submitted its plan two months later, the LLCs advised Majestic that they would ap­prove Majestic’s plan if Majestic agreed to limit its use to a Honda dealership. Majestic agreed to this condition, although it was not required under the lease.

A North Attleborough landlord tried to “extort” benefits from a Honda dealership tenant, according to a Superior Court judge, eventually leading to an over $20 million judgement against the owner.

Surprisingly, the LLCs next sent Majestic a lease termination letter.

When Majestic tried to resuscitate the deal, Dos Anjos expressed interest in reinstating the lease if Majestic agreed to sell the adja­cent property to the LLCs for $1 and add the property to the lease with no additional rent.

Majestic was amenable to this arrange­ment, and Dos Anjos’s lawyer sent Majestic a draft lease reinstatement agreement. Two months later, however, the LLCs sent Majes­tic a letter confirming the lease termination and returned Majestic’s rent checks. Majes­tic sued the LLCs in Superior Court.

Court Awards Double Damages Twice

A jury found that the LLCs had breached the lease, and a Superior Court judge con­cluded that their attempts to terminate the lease were mere pretexts concealing bitter­ness over Majestic purchasing the adjacent land.

This conduct amounted to a violation of Massachusetts General Laws Chapter 93A, which prohibits unfair and deceptive busi­ness practices. The judge found that the LLCs used tactics to “string Majestic along to extort unwarranted benefits,” such as re­stricting Majestic’s use to a Honda dealer­ship, and requiring Majestic to sell the adja­cent property for $1.

The judge awarded Majestic double dam­ages under Chapter 93A, totaling $8,925,000. The judge also ordered the LLCs to cooper­ate with Majestic’s permitting applications.

During the permitting process, Majestic learned that trusts controlled by Dos Anjos, not the LLCs, were the true record owners of the leased premises, contrary to the LLCs’ representations in the lease and Dos Anjos’s sworn testimony.

The LLCs refused to correct this discrep­ancy, causing additional delays to Majestic’s project.

Majestic reopened the superior court case, joining the Dos Anjos trusts in the ac­tion, and claiming further violations of Chapter 93A. The judge awarded additional double damages to Majestic of $3.18 million.

A $20M Judgement

Ultimately, with attorneys’ fees added, and various post judgment maneuvering, Majestic obtained a total monetary judg­ment of over $20 million against the Dos Anjos defendants, with post judgment inter­est accruing at almost $5,000 per day. The Dos Anjos defendants appealed, but the Su­preme Judicial Court upheld the judgment.

While their appeal was pending, the Dos Anjos defendants did something unex­pected – they paid the entire $20 million judgment to Majestic, to avoid accrual of post judgment interest. The Dos Anjos de­fendants eventually lost their appeal, but Majestic still claimed post-judgment interest for the time prior to the SJC’s final decision.

Last month the SJC held that the Dos Anjos defendants’ payment to Majestic halted the accrual of interest, despite the appeal, because Majestic had full, uncondi­tional use of the payment during the appeal.

The Dos Anjos defendants’ payment of the $20 million judgment to Majestic pend­ing the appeal was a risky move. If a defen­dant prevails on appeal, it cannot recover the judgment from a plaintiff that later is unable to repay the defendant.

Dos Anjos’s willingness to pay the $20 million to Majestic showed Dos Anjos’s con­fidence in Majestic’s reliability and good faith. If the Dos Anjos defendants had shown similar qualities in their dealings with Majestic, they could have avoided the harsh result of their misconduct.

Download the article as seen in Banker & Tradesman on April 28, 2025. Learn more about Christopher R. Vaccaro.